Installation and Integration/ActionItems/Cables

From DUNE
Jump to navigation Jump to search

Cable routing decision

Information on current status

Drawings:

APA.png

Xsec.png

PD cables.jpeg

PD Cables 2.jpeg

Concerns and questions

  • How difficult is it to bring the cables up in the APA frame? How long are the cables? What type of access we need to pass the cables through?
  • Are there any mechanical difficulties to pass the cables up the APA frame? Weight? Space?
  • Grounding and Shiedling: Can we bundle the cables together? Do we need mechanical/electrical separations in the APA frame?
  • If we go along the cryostat wall, we need longer cables. What is the impact of longer cables on readout? Procurement?
  • Is there anyway we can attached the cables on the cryostat wall? At the moment there is no mechanical

Group interface

  • Inst.& Int.: Roxanne, Bill, Marvin
  • APA: PSL (Lee and Dan) and Daresbury (Jo)
  • PD: David, Leon and Gary
  • CE: Matt

Potential testing sites

  • Ash River (contact: Bill)
  • Daresbury (contact: Jo)